Name of Service Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act Total Number of Applications Received Total Number of Applications Processed Total Number of Applications Approved Total Number of Applications Rejected Average Time Taken To Grant Approval Median Time Taken to Grant Approval
Provisional NOC 30 217 186 149 37 16 Day(s) 12 application(s) in 14 day(s)
Final NOC 30 105 80 59 21 18 Day(s) 7 application(s) in 24 day(s)
Renewal Final NOC 30 288 222 147 75 17 Day(s) 11 application(s) in 16 day(s)
Name of Service Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act Total Number of Applications Received Total Number of Applications Processed Total Number of Applications Approved Total Number of Applications Rejected Average Time Taken To Grant Approval Median Time Taken to Grant Approval
Provisional NOC 30 90 73 55 18 17 Day(s) 5 application(s) in 9 day(s)
Final NOC 30 43 29 16 13 15 Day(s) 2 application(s) in 4 day(s)
Renewal Final NOC 30 117 94 79 15 14 Day(s) 9 application(s) in 10 day(s)
Name of Service Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act Total Number of Applications Received Total Number of Applications Processed Total Number of Applications Approved Total Number of Applications Rejected Average Time Taken To Grant Approval Median Time Taken to Grant Approval
Provisional NOC 30 3 1 1 0 9 Day(s) 1 application(s) in 9 day(s)
Final NOC 30 1 0 0 0 - -
Renewal Final NOC 30 21 11 4 7 16 Day(s) 2 application(s) in 15 day(s)
Name of Service Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act Total Number of Applications Received Total Number of Applications Processed Total Number of Applications Approved Total Number of Applications Rejected Average Time Taken To Grant Approval Median Time Taken to Grant Approval
Provisional NOC 30 124 112 93 19 15 Day(s) 10 application(s) in 19 day(s)
Final NOC 30 61 51 43 8 19 Day(s) 6 application(s) in 24 day(s)
Renewal Final NOC 30 150 117 64 53 19 Day(s) 6 application(s) in 21 day(s)