| Name of Service | Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act | Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval |
|---|---|---|---|---|---|---|---|
| Provisional NOC | 30 | 258 | 230 | 187 | 43 | 15 Day(s) | 16 application(s) in 14 day(s) |
| Final NOC | 30 | 118 | 116 | 77 | 39 | 17 Day(s) | 9 application(s) in 22 day(s) |
| Renewal Final NOC | 30 | 332 | 310 | 213 | 97 | 17 Day(s) | 15 application(s) in 16 day(s) |
| Name of Service | Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act | Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval |
|---|---|---|---|---|---|---|---|
| Provisional NOC | 30 | 103 | 93 | 72 | 21 | 17 Day(s) | 6 application(s) in 14 day(s) |
| Final NOC | 30 | 51 | 51 | 22 | 29 | 15 Day(s) | 3 application(s) in 22 day(s) |
| Renewal Final NOC | 30 | 136 | 126 | 104 | 22 | 14 Day(s) | 10 application(s) in 10 day(s) |
| Name of Service | Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act | Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval |
|---|---|---|---|---|---|---|---|
| Provisional NOC | 30 | 3 | 3 | 3 | 0 | 12 Day(s) | 1 application(s) in 9 day(s) |
| Final NOC | 30 | 0 | 0 | 0 | 0 | - | - |
| Renewal Final NOC | 30 | 27 | 25 | 15 | 10 | 17 Day(s) | 3 application(s) in 21 day(s) |
| Name of Service | Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act | Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval |
|---|---|---|---|---|---|---|---|
| Provisional NOC | 30 | 152 | 134 | 112 | 22 | 14 Day(s) | 10 application(s) in 11 day(s) |
| Final NOC | 30 | 67 | 65 | 55 | 10 | 18 Day(s) | 6 application(s) in 24 day(s) |
| Renewal Final NOC | 30 | 169 | 159 | 94 | 65 | 19 Day(s) | 9 application(s) in 22 day(s) |