| Name of Service | Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act | Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval |
|---|---|---|---|---|---|---|---|
| Provisional NOC | 30 | 320 | 301 | 244 | 57 | 15 Day(s) | 18 application(s) in 14 day(s) |
| Final NOC | 30 | 156 | 135 | 88 | 47 | 17 Day(s) | 9 application(s) in 22 day(s) |
| Renewal Final NOC | 30 | 383 | 374 | 257 | 117 | 16 Day(s) | 19 application(s) in 16 day(s) |
| Name of Service | Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act | Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval |
|---|---|---|---|---|---|---|---|
| Provisional NOC | 30 | 121 | 112 | 89 | 23 | 17 Day(s) | 6 application(s) in 9 day(s) |
| Final NOC | 30 | 63 | 59 | 26 | 33 | 15 Day(s) | 3 application(s) in 22 day(s) |
| Renewal Final NOC | 30 | 143 | 140 | 117 | 23 | 14 Day(s) | 10 application(s) in 11 day(s) |
| Name of Service | Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act | Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval |
|---|---|---|---|---|---|---|---|
| Provisional NOC | 30 | 6 | 6 | 5 | 1 | 11 Day(s) | 1 application(s) in 9 day(s) |
| Final NOC | 30 | 1 | 1 | 1 | 0 | 13 Day(s) | 1 application(s) in 13 day(s) |
| Renewal Final NOC | 30 | 37 | 35 | 21 | 14 | 16 Day(s) | 3 application(s) in 15 day(s) |
| Name of Service | Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act | Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval |
|---|---|---|---|---|---|---|---|
| Provisional NOC | 30 | 193 | 183 | 150 | 33 | 14 Day(s) | 14 application(s) in 19 day(s) |
| Final NOC | 30 | 92 | 75 | 61 | 14 | 18 Day(s) | 6 application(s) in 18 day(s) |
| Renewal Final NOC | 30 | 203 | 199 | 119 | 80 | 18 Day(s) | 10 application(s) in 16 day(s) |