| Name of Service | Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act | Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval |
|---|---|---|---|---|---|---|---|
| Provisional NOC | 30 | 384 | 360 | 291 | 69 | 15 Day(s) | 22 application(s) in 11 day(s) |
| Final NOC | 30 | 178 | 170 | 114 | 56 | 16 Day(s) | 10 application(s) in 15 day(s) |
| Renewal Final NOC | 30 | 451 | 421 | 290 | 131 | 16 Day(s) | 24 application(s) in 16 day(s) |
| Name of Service | Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act | Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval |
|---|---|---|---|---|---|---|---|
| Provisional NOC | 30 | 139 | 128 | 101 | 27 | 17 Day(s) | 7 application(s) in 16 day(s) |
| Final NOC | 30 | 72 | 68 | 33 | 35 | 14 Day(s) | 3 application(s) in 9 day(s) |
| Renewal Final NOC | 30 | 149 | 145 | 122 | 23 | 14 Day(s) | 11 application(s) in 11 day(s) |
| Name of Service | Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act | Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval |
|---|---|---|---|---|---|---|---|
| Provisional NOC | 30 | 8 | 7 | 5 | 2 | 11 Day(s) | 1 application(s) in 9 day(s) |
| Final NOC | 30 | 1 | 1 | 1 | 0 | 13 Day(s) | 1 application(s) in 13 day(s) |
| Renewal Final NOC | 30 | 39 | 39 | 24 | 15 | 15 Day(s) | 3 application(s) in 15 day(s) |
| Name of Service | Time Limit Prescribed as per the Public Service Guarantee Act or Equivalent Act | Total Number of Applications Received | Total Number of Applications Processed | Total Number of Applications Approved | Total Number of Applications Rejected | Average Time Taken To Grant Approval | Median Time Taken to Grant Approval |
|---|---|---|---|---|---|---|---|
| Provisional NOC | 30 | 237 | 225 | 185 | 40 | 14 Day(s) | 17 application(s) in 11 day(s) |
| Final NOC | 30 | 105 | 101 | 80 | 21 | 17 Day(s) | 9 application(s) in 15 day(s) |
| Renewal Final NOC | 30 | 263 | 237 | 144 | 93 | 17 Day(s) | 13 application(s) in 16 day(s) |